Cost Monitoring
Case Studies
Public Waste Refuse and Recycling Depot
Project: Clugston Group - Waste Refuse and Recycling Depot
Location: Reading
Client: Earthtech
Service: Cost Audit JV project
Approx Value: £11 million
Summary: BPM were appointed by our client to carry our a cost audit. The purpose of the audit was to identify and determine if all costs were correctly accounted, recorded and included by the Commercial and Accounts departments, within the Contract Report and reported on the JV Contract Cost Report. This depot was a waste recycling and waste recovery facilities, for use by both domestic and commercial sectors.